Jaipur: The IPD Tower mission beneath development at Sawai Mansingh Hospital has been delayed by nearly a yr. Due to very large delays within the mission, it’s anticipated to be accomplished by subsequent November as an alternative of this November. At the identical time, efforts to beat the challenges going through the mission have additionally not been profitable for the time being. Why is that this the situation of this formidable mission?
This formidable mission was began through the earlier Congress authorities because the tallest medical tower within the nation. Its basis stone was laid on 5 April 2022 within the presence of famend docs from throughout the nation. First of all, allow us to provide you with full details about this mission costing greater than Rs 600 crore.
-When the muse stone of the IPD Tower mission was laid, its unique value was Rs 456 crore.
-Later, making many modifications within the design of the mission, three service flooring had been additionally added to the design.
Due to this, Rs 60 crore extra had been accredited because of enhance in its value through the time of Congress authorities.
-Another quantity of Rs 99 crore is required to finish this mission as per the preliminary unique design.
-In this respect the price of this mission is round Rs 615 crore.
-Two basements, floor flooring and higher 24 flooring are proposed on this mission.
-If we take away the three service flooring added later, then mainly this mission is simply 24 storeys.
-This IPD tower has 1243 beds, 20 operation theatres, 4 cath labs, 100 OPD registration counters.
-And world class mortuary facility is proposed
-A helipad can also be to be constructed on the roof of the tower for emergencies.
-The completion date of the mission is November 2024.
-The current authorities determined to evaluate this mission
-This was mentioned within the evaluate assembly of the Urban Development Department chaired by Chief Secretary Sudhansh Pant.
-In the assembly of the Empowered Committee of the mission held on June 11, it was determined to make the complete mission solely 24 storeys.
Medical Minister Gajendra Singh Khinvsar, Urban Development Minister Jhabar Singh Kharra, high officers of Urban Development Department, Medical Education Department, JDA, Sawai Mansingh Hospital and Housing Board had been current within the assembly of the Empowered Committee of the mission held on June 11. In this assembly, it was determined in precept that this mission shall be made solely 24 storeys as per its unique design. Let us inform you what choices had been taken on this assembly concerning the mission.
-Medical Education Department will quickly give Rs 99 crore to JDA to make the mission 24 storey.
Housing Board may also pay the excellent quantity of its share within the mission of Rs 163.42 crore.
-Apart from this, the Medical Education Department may also pay the already excellent quantity of Rs 50.48 crore of its share.
-It was additionally determined within the assembly that till the Housing Board and Medical Education Department pay their dues
-Till then JDA will work solely as much as the fifteenth flooring of this 24-storey mission.
-Floors above it is not going to be constructed
-It was determined within the mission that the required quantity for the mission shall be raised quickly.
More than three and a half months have handed because the assembly of the Empowered Committee of the mission. Despite this, the situation of the mission stays the identical. Let us inform you how a lot work has been accomplished on the selections of the Empowered Committee and why this mission has been postponed by nearly a yr.
-According to the choice of the Empowered Committee, a complete quantity of Rs 312.90 crore was to be given for the mission.
-But the truth is that until now JDA has not acquired even a single rupee from this.
-Although the Medical Education Department has accredited Rs 37.24 crore.
-This quantity has additionally not been deposited in JDA’s account but
-There is a risk of getting a little bit greater than ten p.c of the quantity required for the mission.
-But this quantity will not be sufficient to finish the mission quickly
-The deadline to finish this mission is November this yr
-Columns and beams are being put in on this 24-storey constructing.
-Procurement will not be being accomplished because of non-availability of funds.
If their procurement had been common, the work of erecting the higher flooring would have continued.
-14 storeys and three further service flooring have been constructed by JDA on the website.
-The construction of the tower has been erected as much as a service flooring above the 14th flooring.
-As per the choice of the Empowered Committee, as an alternative of including extra flooring, JDA is doing the ending work of the decrease flooring.
-According to consultants, even when all of the required quantity remains to be accessible
-It will take a whole lot of time to regularize the procurement of metal columns and beams.
-In such a scenario, consultants are expressing full apprehension that the mission shall be accomplished solely by November subsequent yr.
Along with the requirement of funds for the IPD Tower mission, it is usually essential to widen the strategy street of the mission and make enough preparations for parking. Let us inform you why street widening and parking preparations are needed and the way a lot work has been accomplished thus far on this path.
-The street connecting JLN Marg and Tonk Road adjoining to IPD Tower is simply 50 toes on the spot.
-This street is to be widened by 100 toes
-Sawai Mansingh Hospital will not be solely the largest hospital of Rajasthan but additionally ranks among the many main hospitals of North India.
-Due to this, numerous sufferers from Rajasthan and out of doors states come right here for remedy.
-The street connecting JLN Marg and Tonk Road adjoining to IPD Tower is simply 50 toes on the spot.
-Due to the massive crowd of sufferers and their households on this hospital, this street must be widened by 100 toes.
-This mission was began through the earlier Congress authorities however enough parking was not organized for the individuals coming right here.
According to consultants, in view of the growing load of sufferers right here, there’s a want for a parking house with the capability of numerous autos.
-The street was not widened and enough parking was not offered.
-So this IPD tower will turn out to be a explanation for main bother as an alternative of comfort for the sufferers and their households.
-In the assembly of the Empowered Committee of the mission, it was determined that the land of Maharaja College campus can be taken to widen the street.
-For this, the state authorities will take into account and resolve at a better degree.
-But until now no concrete motion has been initiated on this matter.
-In the committee assembly, it was agreed to begin work on the plan for development of parking zone quickly.
-The Medical Education Department has despatched a proposal of about Rs 117 crore to the Finance Department to develop the parking zone.
-Various choices have been given within the proposal for the development of parking areas for 800 to 1000 four-wheelers.
-But it has not but been determined the place the parking shall be constructed and which company will construct it.