    Jaipur: Taking a lesson from the Bhankrota tragedy, NHAI has eliminated 57 unlawful median cuts and entry factors on the freeway made by native individuals and others on Gurgaon-Kotputli-Jaipur-Kishangarh NH 48 and Jaipur-Ringas, Jaipur-Tonk-Deoli and Ringas-Sikar routes. Stopped it by operating a marketing campaign. Along with this, to additional ease the visitors on Jaipur-Ajmer route, visitors began on Kamla Nehru Nagar flyover.

    – 21 out of 27 median cuts closed on Rajasthan border Fatehpur-Salasar NH 52 and 58.
    – 10 out of 11 median cuts closed in Gurgaon-Kotputli-Jaipur space NH 48 Package-1.
    – All 12 median cuts closed in Gurgaon-Kotputli-Jaipur space NH 48 Package-2.
    – Both median cuts of Jaipur-Ringas NH 52 closed.
    – All 4 median cuts of Jaipur-Tonk-Deoli NH 52 closed
    -All eight unlawful entry factors of Ringas-Sikar and Jaipur-Ringas closed.

    Whether every other division has discovered a lesson from the Hriday MLA accident that occurred on the morning of December 20 at Bhankrota on Ajmer Road, NHAI has positively launched a marketing campaign to strengthen street security at its stage. Under the management of NHAI Jaipur Project Director Ajay Arya, a workforce of involved concessionaires and impartial engineers have closed unlawful median cuts and entry factors between Gurgaon to Kotputli and Jaipur and Jaipur to Kishangarh. A complete of 58 median cuts and eight unlawful entry factors had been produced from Rajasthan border to Fatehpur to Salasar, from Gurgaon to Jaipur and Kishangarh, between Jaipur-Ringas and Jaipur-Tonk-Deoli. Despite opposition from the native individuals, the NHAI workforce with the assistance of police and native administration has closed all of the eight unlawful entry factors and together with this, 50 out of 58 median cuts have additionally been closed.

    Traffic began on Kamla Nehru Nagar flyover:
    The remaining can even be closed in a day or two. Along with this, visitors has began on Kamla Nehru Nagar flyover. Trial was began on it within the morning. After the success of the trial, visitors was began on three lanes from Ajmer to Jaipur and within the night, three lanes from Jaipur to Ajmer. But additionally the visitors began. By 3:00 pm tomorrow, visitors can even be began on the junction beneath Kamla Nehru flyover. Vijay Prakash Yadav, Deputy Project Manager of GK Associates, says that after onerous work day and night time, visitors has been began on Kamla Nehru Nagar flyover and the work on Bhankrota flyover can even be accomplished by March.

    DPR of two extra flyovers is being ready:
    With this, visitors will begin on the flyover in any respect the ten black spots between Jaipur and Kishangarh. The visitors strain between Jaipur and Ajmer can even be decreased and the issue of visitors jam can even be relieved. Now, after coming down from Kamla Nehru Nagar flyover on Ajmer Road, the visitors police should improve the time of cease gentle there in order that the visitors strain there may be decreased. NHAI Project Director Ajay Arya says that common monitoring of visitors on Ajmer Road is being carried out. Capacity augmentation work has additionally been began close to Balaji of Bad and DPR of two extra flyovers is being ready.